Projects
Project Background
This contract provides for the installation of approximately 2,300 LF of 6-inch, 8-inch, 10-inch, and 12-inch diameter water main and street reconstruction with fiber reinforced hot mix asphalt on five (5) streets. Work to include pavement removal, paving, adjustment of utility appurtenances, striping, water service line, meters, valves, transfer of water services, connections to existing water system, water main abandonments, and lawn restoration and other work
Update 6/8:
Franz St SE will be closed to through traffic on Saturday, 6/10. Detour routes will be provided.
Expect delays and use alternate routes if possible.
Update 5/17:
Night Work at 7th Ave SE: Utility adjustments are scheduled at 7th Ave SE, Golf Club Rd SE, and Golf Club Pl SE from the hours of 7 PM – 7 AM, Wednesday, 5/17 – Friday, 5/19.
Expect delays and use alternate routes if possible. This work is weather dependent and may be rescheduled to a later date.
If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 413-4343.
Update 5/5:
14th Ave SE will be closed between College St SE and Sleater Kinney Rd SE on Monday, 5/8 for paving. Detour routes will be provided. Flaggers will be stationed to permit traffic through the Golf Club Rd SE/14th Ave SE intersection.
Night Work at 7th Ave SE: Paving is scheduled at 7th Ave SE, Golf Club Rd SE, and Golf Club Pl SE from the hours of 7 PM – 7 AM, Tuesday, 5/9 – Friday, 5/12. Expect delays and use alternate routes if possible. This work is weather dependent and may be rescheduled to a later date.
Update 4/28:
Paving is scheduled at 7th Ave SE, Golf Club Rd SE, and Golf Club Pl SE from the hours of 7 PM – 7 AM, Monday – Friday. Expect delays and use alternate routes if possible. This work is weather dependent and may be rescheduled to a later date.
Paving on 14th Ave SE
Update 4/26:
Due to unforeseen circumstances, the paving work on 14th Ave SE that was scheduled for Thursday, 4/27, has been cancelled. This work will be rescheduled for a later date.
Update 4/25:
14th Ave SE will be closed between College St SE and Sleater Kinney Rd SE on Thursday, 4/27 for paving. Detour routes will be provided. Flaggers will be stationed to permit traffic through the Golf Club Rd SE/14th Ave SE intersection. Expect delays and use alternate routes if possible. This work is weather dependent and may be rescheduled to a later date.
Update 4/20: Paving has been tentatively rescheduled on 14th Ave SE between College St and Sleater Kinney Rd SE from Wednesday 4/19 – Friday, 4/21 to Wednesday 4/24 – Thursday, 4/27. This work is weather dependent. Traffic will be reduced to one lane; Expect delays and use alternate routes if possible. Final paving of 14th Ave SE between College St SE and Sleater Kinney Rd SE will occur at a later date.
If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 239-2105.
May 17, 2023
Night Work at 7th Ave SE
Night Work at 7th Ave SE: Utility adjustments are scheduled at 7th Ave SE, Golf Club Rd SE, and Golf Club Pl SE from the hours of 7 PM – 7 AM, Wednesday, 5/17 – Friday, 5/19.
Expect delays and use alternate routes if possible. This work is weather dependent and may be rescheduled to a later date.
If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 413-4343.
May 5, 2023
Construction work Week May 8 through May 12
14th Ave SE will be closed between College St SE and Sleater Kinney Rd SE on Monday, 5/8 for paving. Detour routes will be provided. Flaggers will be stationed to permit traffic through the Golf Club Rd SE/14th Ave SE intersection.
Night Work at 7th Ave SE: Paving is scheduled at 7th Ave SE, Golf Club Rd SE, and Golf Club Pl SE from the hours of 7 PM – 7 AM, Tuesday, 5/9 – Friday, 5/12. Expect delays and use alternate routes if possible. This work is weather dependent and may be rescheduled to a later date.
April 28, 2023
Night Work - Paving on 7th Ave SE Starting Monday, May 1st
Paving is scheduled at 7th Ave SE, Golf Club Rd SE, and Golf Club Pl SE from the hours of 7 PM – 7 AM, Monday – Friday. Expect delays and use alternate routes if possible. This work is weather dependent and may be rescheduled to a later date.
If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 413-4343.
April 26, 2023
Paving Cancelled
Due to unforeseen circumstances, the paving work on 14th Ave SE that was scheduled for Thursday, 4/27, has been cancelled. This work will be rescheduled for a later date.
April 25, 2023
Paving update
14th Ave SE will be closed between College St SE and Sleater Kinney Rd SE on Thursday, 4/27 for paving. Detour routes will be provided. Flaggers will be stationed to permit traffic through the Golf Club Rd SE/14th Ave SE intersection. Expect delays and use alternate routes if possible. This work is weather dependent and may be rescheduled to a later date.
If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 413-4343.
April 21, 2023
Paving rescheduled - College St to Sleater Kinney Rd SE on 14th for 4/24 thru 4/27
Paving has been tentatively rescheduled on 14th Ave SE between College St and Sleater Kinney Rd SE from Wednesday 4/19 – Friday, 4/21 to Wednesday 4/24 – Thursday, 4/27. This work is weather dependent. Traffic will be reduced to one lane; Expect delays and use alternate routes if possible. Final paving of 14th Ave SE between College St SE and Sleater Kinney Rd SE will occur at a later date.
April 14, 2023
Tentative Paving on 14th Scheduled for Wed-Fri April 19-21
Paving is tentatively scheduled on 14th Ave SE between Golf Club Rd SE and Sleater Kinney Rd SE from Wednesday 4/19 – Friday, 4/21. This work is weather dependent. Traffic will be reduced to one lane; Expect delays and use alternate routes if possible. Final paving of 14th Ave SE between College St SE and Sleater Kinney Rd SE will occur at a later date.
If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 239-2105.
April 13, 2023
Paving on 14th Scheduled for Friday, April 14
Paving is scheduled on 14th Ave SE between College St SE and Golf Club Rd SE on Friday, 4/14. Traffic will be reduced to one lane. Expect delays and use alternate routes if possible. Grinding and paving of 14th Ave SE between Golf Club Rd SE and Sleater Kinney Rd SE will occur at a later date.
If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 239-2105.
March 7, 2023
Night Work Beginning Monday, March 13th
Miles Resources, LLC is working to prepare for and connect new utilities in the areas of 14th Ave SE (between Sleater Kinney Rd Se and Golf Club SE), 7th Ave SE (between Sleater Kinney Rd SE and Woodland Square), and Franz St SE. Work will occur in the project area of 14th Ave through February.
Additional notice will be provided for customers impacted by temporary utility shutdowns. Access will be maintained to Intercity Transit, NTPS routes and Lacey Fire District 3. Expect traffic delays and temporary closures over the next few months; Use alternate routes if possible.
Miles Resources, LLC is working to prepare for and connect new utilities in the areas of 14th Ave SE (between Sleater Kinney Rd Se and Golf Club SE), 7th Ave SE (between Sleater Kinney Rd SE and Woodland Square), and Franz St SE. Additional notice will be provided for customers impacted by temporary utility shutdowns. Access will be maintained to Intercity Transit, NTPS routes and Lacey Fire District 3. Expect traffic delays and temporary closures over the next few months; Use alternate routes if possible.
Road grinding and paving are tentatively scheduled on 14th Ave SE Monday, 3/13 – Friday, 3/17. PSE will be relocating utilities on Franz St SE Thursday and Friday, 3/16-17.
Night Work Beginning Monday, March 13th
Work in the area of 7th Ave SE and Golf Club Rd SE will occur at night between the hours of 9:00 PM – 5:00 AM to minimize impacts to traffic and businesses.
If you have any immediate construction concerns you can call the project inspector, Dave Weissenfluh, at (360) 701-9015.
January 27, 2023
Project Start Up
Miles Resources, LLC is working to prepare for and connect new utilities in the areas of 14th Ave SE (between Sleater Kinney Rd Se and Golf Club SE), 7th Ave SE (between Sleater Kinney Rd SE and Woodland Square), and Franz St SE. Work will occur in the project area of 14th Ave through February.
Additional notice will be provided for customers impacted by temporary utility shutdowns. Access will be maintained to Intercity Transit, NTPS routes and Lacey Fire District 3. Expect traffic delays and temporary lane closures over the next few months; Use alternate routes if possible.
If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 413-4343.