2022 Overlay

Project Background

This contract provides for street reconstruction and hot mix asphalt overlays of fourteen (14) streets, to include road removal, minor reconstruction, adjustments of utility appurtenances, striping and other work.

The City has awarded the construction contract to Lakeside Industries Inc. If you have any coordination or construction issues you can contact the City of Lacey project inspector Dave Weissenfluh at 360-701-9015.


Sign up for email notifications here!

Tentative Schedule


To view larger calendar, click on the corresponding calendar above. 

Locations of work

To view larger maps, click on the corresponding map above.

September 16, 2022

Section of Marvin Rd Closed from 32rd Ave to 33rd Way

Paving on the final section of Marvin Rd begins Monday, 9/19 and will continue through Tuesday evening (7:00 AM – 9:00 PM). There will be road closures between 31st Ave NE and Hawks Prairie Rd NE (at 33rd Ave NE). Detour routes will be posted and local access provided with flaggers. Expect delays when traveling and use alternative routes if possible. Click link below for locations of work and detour routes.

If you have any immediate construction concerns you can call the project inspector, Dave Weissenfluh, at (360) 701-9015.

August 30, 2022

Marvin Rd Paving

Paving on Marvin Rd begins today and will go on through the end of next week. There will be no road closure or signed detours, but you can expect minor delays when traveling. For the up coming holiday weekend, construction will stop at 12:00 pm on Friday and resume on Tuesday morning. Click link below for days and locations of work.

Marvin Rd Paving Map

If you have any immediate construction concerns you can call the project inspector, Dave Weissenfluh, at 360-701-9015.

August 24, 2022

Road Closures

Royal St SE will be closed on Wednesday August 24 for paving.  Nelson Rd SE will be closed on Wednesday August 24 and Thursday August 25 for paving. 

Campus Highlands Drive, in-between Willamette Dr NE and Cameron Ln NE, will be closed on Thursday August 25 & Friday August 26 for paving.

Campus Highlands Drive – Road Closure Map

If you have any immediate construction concerns you can call the project inspector, Dave Weissenfluh, at 360-701-9015.  

August 17, 2022

The Arbors Neighborhood Paving

Paving in the Arbors neighborhood begins today. Click on the paving schedule link below to see how you might be affected. Paving on Royal St & Nelson Rd SE is tentatively scheduled to start next Wednesday, August 24th. For additional schedules, check out the lookahead linked below.

The Arbors Paving Schedule August 17-19, 2022 – Click Here
Lookahead Schedule – Click Here

If you have any immediate construction concerns you can call the project inspector, Dave Weissenfluh, at 360-701-9015.  
——————————————————————————————————————————————————————————–
Previous Email Notifications:

2022 Overlay Project Update – August 9, 2022

 

August 11, 2022

Mobilization Thursday August 11

Lakeside Industries Inc, of Lacey WA plan to mobilize THIS Thursday August 11. They will begin their work in the Arbors Neighborhood. With Roadway Prep and lower utility work 8-11 thru 8-15. Road Excavation will tentatively start Tuesday 8-16.

Lookahead Schedule and map of The Arbors neighborhood

Royal St and Nelson Rd SE tentatively have their start of roadway prep on Tuesday 8-23.