Project Background

The contract has been awarded to Northwest Cascade Inc.  We will hold a preconstruction meeting with the contractor later in April.  As soon as we have an anticipated schedule and start date we will post an update.

PROJECT DESCRIPTION
This Contract provides for construction of approximately 1,300 LF of 12-inch and 8-inch gravity sewer main that will connect an existing sewer main located on 5th Ct SE to another existing sewer main located at the Motor Controls Park at 426 Carpenter Road SE. Work to include demolition of an existing single family manufactured home and supporting structures, decommissioning an existing lift station site including converting a wet well into a manhole, construction of a new manhole, service lines, decommissioning of septic systems (permits required), connections to existing sewer and water systems, sewer and main abandonments and extensions, pavement and lawn restoration and other work.

 

Paving Information

The contractor is tentatively planning on paving the end of the cul-de-sac on Monday, September 19, 2022. The specific locations can be seen below in the shaded area. As part of this we would ask that any cars parked on the roadway, please be moved into the driveway or on the street outside of the shaded area. Access to individual driveways will be restricted as the paving machine passes by until the asphalt is cool enough to drive over. 

On 5th CT SE, paving begins at 8:00 am and cars will need to be off the road prior.

On Kinwood Park Ln SE, paving begins at 10:00 am and cars will need to be off the road prior.

September 15, 2022

Paving on 5th CT SE and Kinwood Ln SE

The contractor is tentatively planning on paving the end of the cul-de-sac on Monday, September 19, 2022. The specific locations can be seen below in the shaded area. As part of this we would ask that any cars parked on the roadway, please be moved into the driveway or on the street outside of the shaded area. Access to individual driveways will be restricted as the paving machine passes by until the asphalt is cool enough to drive over. If you are needing access to a car parked in the driveway during this time, we highly recommend that it be parked on the street outside of the shaded area to prevent any delays.


On 5th CT SE, paving begins at 8:00 am and cars will need to be off the road prior.

On Kinwood Park Ln SE, paving begins at 10:00 am and cars will need to be off the road prior.

August 25, 2022

Installation of sewer continues and is expected to be completed by mid September.

August 8, 2022

Week 2

Installation of sewer continues.

Contractor will be paving cul-de-sac and parking area at 426 Carpenter Rd SE on Wednesday August 10th.

August 1, 2022

Week 1

City Owned house at 6612 5th Ct SE has been demoed. Some trees have been removed in addition to clearing and grabbing prep work.

Installation of 12-inch gravity sewer main underway.

July 11, 2022

Mobilization

Northwest Cascade Inc will be mobilizing on site on Monday July 25. There is a tentative completion sometime in the middle of November 2022.