Project Background

This contract provides for a partial street reconstruction and hot mix asphalt overlay for a portion of 65th Ave SE in the Capitol City Golf Club Estates community. The work is to include bituminous surface planing, asphalt and concrete paving, ditch excavation, storm drain construction, adjustments of utility appurtenances, and other work.

Contract was awarded to Russ Construction and will be mobilizing on site December 1st.

Updated 2/21/2024

Paving will occur in the highlighted area(s) on Thursday, February 22nd. Traffic will be reduced to one lane; please use alternate routes if possible. This work is weather dependent. Please call the Project Inspector, Kevin Cools, with any questions or immediate concerns at 360-239-2105. 

Sign up for Capitol City Golf Course - Stormwater Improvements Email Notifications:      *


By submitting this form, you are consenting to receive marketing emails from the City of Lacey. You can revoke your consent to receive emails at any time by using the SafeUnsubscribe® link, found at the bottom of every email. Emails are serviced by Constant Contact.

February 21, 2024

Paving Thursday February 22 & Friday February 23

Paving will occur in the highlighted area(s) on Thursday, February 22nd. Traffic will be reduced to one lane; please use alternate routes if possible. This work is weather dependent. Please call the Project Inspector, Kevin Cools, with any questions or immediate concerns at 360-239-2105. 

November 30, 2023

Mobilization

We would like to inform you that construction of the Capitol City Golf Course – Stormwater Improvements project is scheduled to begin on Friday, December 01, 2023 and is expected to be completed early February, depending on weather.

This project will construct new stormwater facilities along approximately a 500-foot portion of the south side of 65th Ave SE in the Capitol City Golf Club Estates community. The improvements will also consist of a partial street reconstruction including hot mix asphalt overlay and minor concrete paving. Thank you for your continued patience as we complete this project