Projects

Carpenter Road/Britton Parkway Roundabout

6643 Britton Ln NE, Lacey, WA 98516, USA

Public Works Projects

Department: Public Works

Project Background

This contract provides for construction of a modern roundabout to include; pavement rehabilitation, private utilities, stormwater, water, sewer, illumination, landscaping and other work.

Update 3/21/2024

Traffic Lane Shift with Intermittent Closures

Traffic is still reduced to one lane each way at Carpenter Rd NE/Britton Parkway NE/Draham St NE for roadway preparation.  This shift will remain in effect through May, followed by another temporary lane shift. Flaggers will be stationed to direct traffic at intersections. Please use alternate routes if possible.

This project has an anticipated timeline of work through September 2024. If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 413-4343.

Sign up for Carpenter Road/Britton Parkway Roundabout Email Notifications:      *


By submitting this form, you are consenting to receive marketing emails from the City of Lacey. You can revoke your consent to receive emails at any time by using the SafeUnsubscribe® link, found at the bottom of every email. Emails are serviced by Constant Contact.

March 21, 2024

Traffic Lane Shift with Intermittent Closures

Traffic is still reduced to one lane each way at Carpenter Rd NE/Britton Parkway NE/Draham St NE for roadway preparation.  This shift will remain in effect through May, followed by another temporary lane shift. Flaggers will be stationed to direct traffic at intersections. Please use alternate routes if possible.

March 16, 2024

The Contractor continues to work on clearing the hillsides surrounding the Carpenter & Britton intersection.  Traffic will continue to flow under one-way control.  Lane closures are anticipated for the upcoming future, including shifting traffic to a new alignment starting on Tuesday, March 19, 2024.

Work has begun to locate existing underground utilities, paving will be performed for the new roadway alignment, and Utility Companies will be working in the area to relocate lines in preparation of the new roundabout.

The public is notified to find alternative routes around the area as work progresses to minimize wait time through the one-way lane closures throughout the next month.

March 1, 2024

Intermittent Lane Closures

Traffic will be reduced to one lane each way at Carpenter Rd NE/Britton Parkway NE/Draham St NE beginning Wednesday, 3/6 for roadway preparation.  Flaggers will be stationed to direct traffic at intersections.

February 29, 2024

Mobilization

On January 16, 2024, the City of Lacey awarded the Construction contract to the qualified low-bidder, Active Construction, Inc., of Puyallup, WA. (Contractor). The Contractor will be mobilizing onto the Carpenter and Britton intersection beginning on March 4, 2024.  Initial work includes temporary traffic control set-up, clearing and grubbing, and potholing.  The Contractor will be placing erosion control measures throughout the working project area.

This project has an anticipated timeline of work through September 2024. If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 413-4343.