Projects
Terry Cargil Reservoir
4504b Intelco Loop Southeast, Lacey, WA, USA
Project Background
This contract provides for the installation of a new 1.25 million gallon composite elevated water storage tank and associated site utility and stormwater improvements, which includes a new 16-in diameter water main from the proposed tank to the existing water main on Intelco Loop SE, south of the tank site, new telemetry/SCADA controls for the tank, and onsite detention pond. Work to include meters, valves, connects to existing water system, catch basins, pavement, and lawn restoration, and onsite stormwater improvements.
Sign up for email notifications here!
Road Closure Monday, January 16
Intelco Loop SE will be closed after Roxanna Dr SE (between Horizon Learning Center and TwinStar Credit Union) on Monday, 1/16/2023. Intelco Loop SE will remain open to local traffic with no through access; please use detour route as shown. Click link below for location of work.
This work is weather dependent and may be rescheduled to a later date; Please check back for updates.
If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 413-4343.
August 21, 2024
Road Closure - Intelco Loop
Intelco Loop SE will be closed for paving after Roxanna Dr SE (between Horizon Learning Center and Twinstar Credit Union) beginning Thursday, 8/22 at 3 PM through Tuesday, 8/27. Intelco Loop SE will remain open to local traffic with no through access; please use detour route as shown. This work is weather dependent and may be rescheduled to a later date.
January 10, 2023
Road Closure - Monday, January 16
Intelco Loop SE will be closed after Roxanna Dr SE (between Horizon Learning Center and Twinstar Credit Union) on Monday, 1/16/2023. Intelco Loop SE will remain open to local traffic with no through access; please use detour route as shown. Click link below for location of work.
This work is weather dependent and may be rescheduled to a later date; Please check back for updates.
If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 413-4343.
November 29, 2022
Intelco Loop SE - Opened Up
Intelco Loop SE has opened up with temporary striping. The city thanks you for your patience during this time.
November 10, 2022
Road Closure - Continuing until after Thanksgiving
Intelco Loop SE will be closed after Roxanna Dr SE (between Horizon Learning Center and Twinstar Credit Union) beginning Monday, 10/3 until end of November. Intelco Loop SE will remain open to local traffic with no through access; please use detour route as shown. Click image below for location of work.
If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 413-4343.
September 29, 2022
Road Closure - Beginning 10/3
Intelco Loop SE will be closed after Roxanna Dr SE (between Horizon Learning Center and Twinstar Credit Union) beginning Monday, 10/3 until mid-November. Intelco Loop SE will remain open to local traffic with no through access; please use detour route as shown. Click image below for location of work.
If you have any immediate construction concerns you can call the project inspector, Kevin Cools, at (360) 413-4343.
June 2, 2022
Contractors on site
The contractor, Phoenix Fabricators and Erectors, LLC and their subcontractor BOSS Construction, Inc will be getting started on site this week. The next couple of weeks they will be clearing out brush, installing fence, and removing trees.
The project inspector assigned to this project is Kevin Cools. If you have any immediate construction concerns about this project you can contact him at 360-239-2105.
March 17, 2022
Contract Awarded
The contract has been awarded to Phoenix Fabricators & Erectors. We will hold a preconstruction meeting with the contractor later in April. As soon as we have an anticipated schedule and start date we will post an update.
February 2, 2022
Bid Opening
The project was advertised for approximately seven weeks and bids were opened February 2, 2022. Two (2) bids were received. The two bids ranged from a low of $8,456,619.97 to a high of $11,130,355.96. Phoenix Fabricators & Erectors, LLC from Avon, IN is the low bidder at $8,456,619.91. The Engineer’s Estimate is $11,199,078.43.